Killara 24

Building a single storey Clarendon home

Waterproofing & wet area tiling (Post #17)

The blue one above is first stage, which is done after frames are up. This basically covers all ‘edges’ and drain inlets. The grey one below is the second stage … Continue reading

May 2, 2015 · 3 Comments

Cabinetry (Post #16)

May 2, 2015 · Leave a comment

Little annoying things to look out for (Post #15)

There are a couple of little things which have since cropped up which required me letting the SS know that I am not happy about them. Firstly, the cavity access … Continue reading

February 25, 2015 · 6 Comments

Bricks !!! (Post #14)

On Monday 17th Feb 2015, the brickie larbourer arrived and opened the pallets. He then distributed the bricks around the house putting bricks a few metres apart. Bricks ready to … Continue reading

February 21, 2015 · 1 Comment

More internal work done … pics (Post #13)

So, this last week and two were quite busy at site … After the roof tiles were laid on Friday 06 Feb 2015, all the wiring was done on Monday … Continue reading

February 14, 2015 · Leave a comment

We have a roof ! (Post #12)

Roof was all completed in a day ! 06 Feb 2015 There were atleast 12 of them working on roof today. Guard rails were installed yesterday. So this morning they … Continue reading

February 6, 2015 · Leave a comment

Things getting back to normal…. (Post #11)

So in the third week of Jan 2015 our Site supervisor was changed. Since the new SS has come onboard, there has been progress made, slowly, but surely. he told … Continue reading

February 4, 2015 · Leave a comment

Worst construction experience so far …… (Post #10)

Never ever again with Clarendon. Clarendon was soooo nice when we were in Admin stage. I was happy and was looking forward to the construction starting. But alas, I had … Continue reading

January 14, 2015 · 2 Comments

Site Excavation & Slab (Post #9)

Work on our site started on 04 Nov with Clarendon dumping a load of soil on our land for levelling. There was some cut and fill required on our block … Continue reading

November 13, 2014 · Leave a comment

The Construction process (Post #8)

In this image below is the construction process that Clarendon follow. However you will get a good idea of what comes before and what after ………

November 12, 2014 · 2 Comments