Killara 24

Building a single storey Clarendon home

More internal work done … pics (Post #13)

So, this last week and two were quite busy at site …
After the roof tiles were laid on Friday 06 Feb 2015, all the wiring was done on Monday 09 Feb. This includes electrical, Home theater, data and security. Also the AC ducting, fan coil unit were installed. Ducting for bathroom fans, kitchen rangehood went in as well over a couple of days !
Cavity sliders went in and water[reefing was done same day.
Sisalation (the blue wrap) was done the day after, and then finally on Friday 13th feb, the wall and roof insulation was laid !

They had missed the ducting for fan/heter in ensuite, so had to call supervisor to get it done. But it was easy fixed !

So a pretty eventfull week.

Pics below !

2015-02-12-15h16m14

2015-02-12-15h17m12

2015-02-12-15h19m48

2015-02-12-15h19m41

2015-02-12-15h16m30

2015-02-12-15h20m47

2015-02-12-15h18m44

2015-02-12-15h25m15

2015-02-12-15h15m54

2015-02-12-15h15m51

2015-02-13-15h34m35

2015-02-13-15h30m59

2015-02-12-15h14m15

2015-02-12-15h13m26

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Information

This entry was posted on February 14, 2015 by .
%d bloggers like this: